Izvedba elektromontažnih del, jeklenih konstrukcij z AKZ, in gradbenih del v 220 kV stikališču
Reconstruction of nine 220 kV bays in transformer station Beričevo
Demolition and building construction work
Production, delivery and installation of 25 tons of steel constructions
Restoration of foundations, constructions, lightning and substation relay building
Anti-corrosion protection of 22,7 tons of new and 394,1 tons of existing steel constructions
Installation of high voltage equipment in 220 kV bays
|